Start with loads, not panels

List what must keep running and for how long: lights, Wi-Fi, TV, fridge, alarm, gate, and whether you want geyser or air conditioning included. Multiply each load's power by the hours you want it supported. That total, in kilowatt-hours, is your usable storage requirement.

The details that catch people out

  • Usable versus nominal capacity — lithium batteries should not be planned to 100% depth of discharge.
  • Inverter capacity — storage does not help if the inverter cannot deliver the peak load. Air conditioners and geysers have high starting demand.
  • Essential loads separation — without correct DB work, the system tries to back up the entire house.
  • Recharge time — a battery you cannot refill from your array by the next evening is undersized on the generation side.

Sensible approach

Size the essential-loads board first, then the inverter, then the battery, then the array to refill it. Doing this in the wrong order is why so many systems disappoint.